Manufacturing lead time reduction

Safran Turbomeca

Objectives

  • Identify the resources contributing to lead times and their respective impact.​

  • Define solutions to reduce lead times by 1/3 by the end of 2014, then by a factor of 3 by the end of 2015.

The project was carried out in 3 phases

2013 baseline: ​

  • Flow diagnosis: Workload, queues, manufacturing lead times​

  • Identification of potential solutions

2014 and 2015 outlooks: ​

  • Workload/capacity balancing​

  • Identification of key resources driving lead times​

  • Formulation and combination of solutions to achieve objectives: Reshoring subcontracted operations, reducing specific subcontracting lead times, cutting batch sizes and changeover times, developing labor cross-skilling

Results

  • What the Production Manager said: "A clear, well-supported action list with quantified impacts, allowing us to implement the necessary changes with complete confidence!"​

  • Controlled 43% reduction in manufacturing lead times achieved, compared to the 33% target (2014), ensuring contractual operational performance is met​

  • Resource efficiency in achieving the target results​