Manufacturing lead time reduction
Objectives
Identify the resources contributing to lead times and their respective impact.
Define solutions to reduce lead times by 1/3 by the end of 2014, then by a factor of 3 by the end of 2015.
The project was carried out in 3 phases
2013 baseline:
Flow diagnosis: Workload, queues, manufacturing lead times
Identification of potential solutions
2014 and 2015 outlooks:
Workload/capacity balancing
Identification of key resources driving lead times
Formulation and combination of solutions to achieve objectives: Reshoring subcontracted operations, reducing specific subcontracting lead times, cutting batch sizes and changeover times, developing labor cross-skilling
Results
What the Production Manager said: "A clear, well-supported action list with quantified impacts, allowing us to implement the necessary changes with complete confidence!"
Controlled 43% reduction in manufacturing lead times achieved, compared to the 33% target (2014), ensuring contractual operational performance is met
Resource efficiency in achieving the target results